Signal Free Corridor Walton Road to Lalik Jan Chowk DHA Lahore

Construction of Signal Free Corridor From Walton Road To Lalik Jan Chowk DHA Lahore.

This Project Includes :

Walton Road :     Flyover

PSO Chowk :        Underpass, Flyover (Towards Y Block Phase III)

Masjid Chowk:   Underpass

Ghazi Chowk :   Underpass

Lalik Chowk:     Re-Modeling.

 

Cost:  Rs. 2.450 Million

Client:  DHA Lahore

Widening & Improvments Of Main Sheikhupura Road

Widening & Improvement of Main Sheikhupura Road of 06KM length either side with 3-Lane on each side where 4-Lane in section-II and construction of storm water drain and fixing of curbstones on both sides. Construction of parking along the road fixing tuff pavers in section-I, II & III, where constructed 3KM wall in Section-III. Installation of lighting poles & complete electrical works.

Development of Park 20,000 Sft. (Landscape, Entry Gate, Gazebos, Monuments, walls, Grills, Footpaths & Filling etc.) and Construction of 04 Monuments at Bypass, Batti Chowk, Rafi Chowk & SP Chowk

Cost:                    Rs. 1,229.00 Million

Client:                 Lahore Development Authority (LDA)

Signal Free Corridor – Islamabad Highway

Construction of 04KM of length either side with 4-Lane on each side along-with grade separated facility from Zero Point to Faizabad Interchange and Construction of Interchange at I-8 Intersection, Islamabad including complete Horticulture / Landscaping and Strom water Drainage system(Phase-I).

Cost:                    Rs. 1,578.00 Million

Client:                 Capital Development Authority (CDA)

Bus Rapid Transit System (BRTS) Project Package IIA

Construction of 1.4KM length of 2-Lane BRTS Road including steel bar on both sides, along-with 4-Lane dual carriageway (asphalt work) on each side of the project. Construction of Bus Stations, 02 pedestrian underpasses, culverts and installation of Escalators, Generators, Panels, Lighting Poles etc.

Cost:  Rs. 792 Million

Client: TEPA / LDA

Bus Rapid Transit System (BRTS) Project Package VIII

Construction of Bus Rapid Transit System (BRTS Project) for Lahore-Ferozepur Road Corridor (Package-VIII). Construction of 2.4KM length of 2-Lane BRTS Road including steel bar on both sides, along-with 4-Lane dual carriageway (asphalt work) on each side of the project. Construction of Bus Stations, pedestrian bridges, underpass, culverts and installation of Escalators, Generators, Panels, Lighting Poles etc.

Cost:  Rs. 1,210.00 Million

Client: TEPA / LDA

Bus Rapid Transit System (BRTS) Project Package V

Construction of Bus Rapid Transit System (BRTS Project) for Lahore-Ferozepur Road Corridor (Package-V). Construction of 3.9KM length of 2-Lane BRTS Road including steel bar on both sides, along-with 5-Lane dual carriageway (asphalt work) on each side of the project. Construction of Bus Stations, pedestrian bridges, underpass, culverts and installation of Escalators, Generators, Panels, Lighting Poles etc.

Cost:  Rs. 1,620.00 Million

Client: TEPA / LDA

Islamabad Expressway

Construction of Islamabad Expressway 8 KM either side with 5 lanes on each side in Islamabad. Two (2) outer lanes of Rigid Pavement for heavy traffic and three (3) inner lanes of flexible pavement for light traffic.

Cost:  Rs. 1,283.00 Million

Client:  Capital Development Authority, Islamabad

Western Carriageway, Islamabad

Construction and rehabilitation of 12-Km Rigid Pavement on Western Carriageway (2-lanes) of Islamabad / Rawat Highway from G.T. Road to Airport Chowk (Remaining Works), Islamabad.

Cost:  Rs. 400.00 Million

Client:  Capital Development Authority, Islamabad

Underpass Between H-8/H-9, Islamabad

Construction of Underpass between H-8/H-9 and Contraction of 3 lane Road (Rigid Pavement) on 9th Avenue from Kashmir Highway to I.J. Principal Road, Islamabad.

Cost:  Rs. 463.49 Million

Client:  Capital Development Authority, Islamabad

Lehtrar Road, Islamabad

Dualiation of Lehtrar Road from Tramari Chowk to Pinctech including one bridge, Islamabad.Dualiation of Lehtrar Road from Tramari Chowk to Pinctech including one bridge, Islamabad.

  • No of Lanes 3 Each Side
  • Width of Each lane 3.65 Meters
  • Crush Aggregate 2,200,000 Cubic Feet
  • Crushed Stone Metal 1,980,000 Cubic Feet
  • Lawrencepur Sand 1,500,000 Cubic Feet
  • Reinforced Steel 1,650,000 kg

Cost:  Rs. 1,400.00 Million

Client:  Capital Development Authority, Islamabad